Designs by D&J completed a full rehab of a pre-war apartment on East 72nd Street on the Upper East Side in about 16 weeks (August–December 2024), within a $90,000–$150,000 budget range: a full-gut kitchen, a bathroom refresh, an electrical update, refinished floors, a full repaint, a flushometer-to-standard toilet conversion, and restoration of the apartment’s original locks. The owner was in Hong Kong for the entire project, so we ran it fully remotely under the building’s alteration agreement and board rules.

Project at a glance
| Location | Upper East Side, Manhattan (East 72nd Street) |
| Building type | Pre-war apartment building |
| Scope | Full kitchen gut, bathroom refresh, electrical update, floor refinishing, full repaint, toilet conversion, original lock restoration |
| Budget range | $90,000–$150,000 |
| Building requirements | Alteration agreement, board work rules, certificate of insurance (COI) for every delivery, daily elevator shutdown 12:00–12:30 p.m. |
| Owner involvement | Fully remote — the owner was in Hong Kong |
| Construction time | About 16 weeks (Aug 26 – Dec 19, 2024) |
| Delivered by | Designs by D&J — design-build, owner-led by Joddi “Jay” and Dominique “Dee” Sylvester |
Before
The apartment had its original-era galley kitchen with worn cabinets and an old checkerboard floor, and a bathroom with a pedestal sink, mosaic floor and a commercial-style flushometer toilet.


Scope of work
- Full kitchen gut: demolition to the studs and subfloor, new layout with shaker cabinets, quartz countertops, subway tile backsplash, new sink and appliances.
- New kitchen floor: Schluter DITRA uncoupling membrane over a leveled subfloor, then black-and-white marble-look tile set on the diagonal.
- Bathroom refresh: new vanity with stone top, new faucet and handheld shower, refreshed tile.
- Toilet conversion: replaced the flushometer valve with a standard tank toilet.
- Electrical update: updated wiring and circuits for the new kitchen and lighting, plus new light fixtures including the kitchen chandelier and foyer globe.
- Floors and paint: refinished the original oak floors and repainted the entire apartment.
- Original locks: removed the traditional pre-war locks before work began and reinstalled them in their original state.
Working within building rules — with the owner overseas
This renovation had two constraints that shape many Manhattan projects: a building with strict alteration rules, and an owner who could not be on site. The owner was in Hong Kong from start to finish, so Designs by D&J ran the whole process virtually.
- Alteration agreement and board rules: the work followed the building’s alteration agreement and the board’s renovation rules from the first day.
- Certificates of insurance: every delivery and vendor needed a COI on file with the building before it could arrive, so we coordinated insurance paperwork with each supplier ahead of time.
- Elevator schedule: the building’s elevator shut down daily from 12:00 to 12:30 p.m., so we scheduled deliveries and debris removal around that window.
- Remote owner: selections, decisions and progress updates were handled virtually, giving the owner a clear view of the job from the other side of the world.
How we built it
Pre-war floors are rarely flat or stable enough for large tile. After demolition we leveled the kitchen subfloor and installed Schluter DITRA, an uncoupling membrane that helps protect tile from cracking as an old building moves. We then dry-laid the checkerboard pattern to set the diagonal lines before installing a single tile.



After





After move-in: when a photo doesn’t tell the whole story
Because the owner was overseas, she approved the refinished floors from photos. When she moved in and saw them in person, she wanted a richer stain and a glossier finish. We paused her furniture deliveries, moved what was already in the apartment into the kitchen, and brought the flooring crew back for another coat.
That return visit could have been a change order. We did it at no charge, because a photo sent across the world can’t show everything a floor looks like in daylight. We document every change in writing, but a change order is our last resort, not our first.
Questions about this project
Why replace a flushometer toilet in a pre-war apartment?
Many pre-war buildings were fitted with commercial-style flushometer valves that need high water pressure and large supply lines. Converting to a standard tank toilet makes the bathroom quieter, easier to service and compatible with modern fixtures. The change requires reworking the supply and must follow the building’s plumbing rules.
Can original pre-war hardware be kept during a renovation?
Yes. On this project we removed the apartment’s traditional locks before demolition and reinstalled them in their original state once painting was complete, so the apartment kept its pre-war character.
How long does a pre-war apartment renovation take in Manhattan?
This full kitchen gut, bathroom refresh, electrical update, floor refinishing and full repaint took about 16 weeks of construction, from late August to mid-December 2024. Building approvals, material lead times and work-hour rules can lengthen any project.
Can you renovate my NYC apartment while I’m out of the country?
Yes. On this Upper East Side project the owner was in Hong Kong for the entire renovation. We handled the building’s requirements on site and ran selections, decisions and progress updates virtually.
What building requirements should I expect for a Manhattan apartment renovation?
Many buildings require a signed alteration agreement, compliance with board work rules, and a certificate of insurance (COI) for every contractor and delivery. Some also limit elevator use; in this building the elevator shut down daily from 12:00 to 12:30 p.m.