If you’re planning a renovation in New York City, understanding the NYC Department of Buildings (DOB) permit system is essential. One of the most common sources of confusion for homeowners and contractors alike is the distinction between Alteration Type 1, Alteration Type 2, and Alteration Type 3 permits.
Getting the right permit type matters — filing under the wrong category can cause project delays, inspection failures, or forced stop work orders. This guide explains each alteration type, when each is required, and how to navigate the filing process.
The NYC DOB Alteration Permit System: An Overview
The NYC Department of Buildings requires permits for most renovation work that goes beyond purely cosmetic changes. The permit type required depends primarily on the scope and nature of the work — specifically whether the project changes the building’s use, occupancy classification, or egress configuration.
The three alteration types are defined in the NYC Building Code and administered through the DOB NOW filing system:
Alteration Type 1 (Alt 1): Major Changes to Occupancy or Use
What Is an Alt 1?
An Alteration Type 1 permit is required when a project changes the building’s use or occupancy classification, egress configuration, or number of dwelling units. Alt 1 applications are the most complex and require full plan review by the DOB before any work can begin.
When Is an Alt 1 Required?
- Converting a single-family home to a two-family home (or vice versa)
- Converting a residential building to commercial use (or mixed-use)
- Adding a legal accessory dwelling unit (ADU) in a basement or cellar
- Changing the Certificate of Occupancy to reflect a new use
- Combining or subdividing dwelling units in a way that changes the total unit count
- Projects that affect egress (fire exits, stairways, exit doors)
Alt 1 Process and Timeline
Alt 1 applications require a licensed architect or professional engineer (PE) to prepare and file plans. The DOB reviews plans for compliance with the Building Code, Zoning Resolution, and other applicable regulations. Plan review can take 4–16 weeks depending on project complexity and DOB workload. Once approved, a new or amended Certificate of Occupancy is issued upon project completion.
Alteration Type 2 (Alt 2): Significant Renovations Without Use Change
What Is an Alt 2?
An Alteration Type 2 permit covers significant renovation work that does not change the building’s use, occupancy classification, or number of dwelling units. Alt 2 is the most common permit type for substantial residential renovations in NYC — gut renovations, full bathroom remodels, kitchen renovations with structural work, and system-wide electrical or plumbing upgrades typically fall in this category.
When Is an Alt 2 Required?
- Gut renovations of kitchens, bathrooms, or multiple rooms simultaneously
- Removal of non-bearing walls (in some cases) or any bearing walls
- Significant plumbing modifications (moving drains, adding new plumbing fixtures)
- Full electrical panel upgrades and service changes
- HVAC system installation or major modifications
- Horizontal enlargements or extensions of existing structures
Alt 2 Process and Timeline
Alt 2 applications require a licensed architect or PE to prepare plans (though some may qualify for self-certification). The DOB reviews plans, though many Alt 2 applications can be approved more quickly than Alt 1 filings. Expect 2–8 weeks for plan review under standard filing; professional certification can speed this up. Required inspections occur at key milestones (rough-in, framing, final).
Alteration Type 3 (Alt 3): Limited Alterations
What Is an Alt 3?
An Alteration Type 3 permit covers limited alterations that are minor in scope and do not affect the building’s structure, egress, or primary systems in a significant way. Alt 3 was previously known as a “Limited Alteration Application” (LAA) and is often used for work on individual apartments or small, defined scopes.
When Is an Alt 3 Required?
- Replacing a single bathroom (without moving plumbing or changing egress)
- Minor partition work that doesn’t affect egress or bearing walls
- Installing a new HVAC unit in an existing opening
- Replacing electrical panels within existing apartments (in some buildings)
- Limited cosmetic work that still requires a DOB permit
Alt 3 Process and Timeline
Alt 3 applications generally require fewer documents and have a faster review timeline than Alt 1 or Alt 2. In some cases, Alt 3 work may qualify for professional certification, allowing work to begin more quickly. Alt 3 does not result in a new Certificate of Occupancy.
Choosing the Right Permit Type: A Quick Reference
| Project Type | Permit Required |
|---|---|
| Converting single-family to two-family | Alt 1 |
| Adding a legal basement apartment | Alt 1 |
| Full gut kitchen renovation with structural work | Alt 2 |
| Full bathroom remodel with plumbing relocation | Alt 2 |
| Whole-home rewire | Alt 2 |
| Single bathroom replacement (no plumbing move) | Alt 3 |
| Minor partition work | Alt 3 |
Common Permit Mistakes to Avoid
Many renovation problems stem from permit errors. The most common mistakes include filing under the wrong alteration type, starting work before permits are approved, failing to schedule required inspections, and not obtaining a sign-off (final inspection) at project completion.
Unpermitted work creates serious problems when you sell: buyers’ attorneys and title companies routinely flag open permits and violations, and clearing them up can be costly and time-consuming.
How Designs by D and J Navigates the NYC Permit Process
At Designs by D and J, we manage the entire NYC permit process for our clients — from determining the correct alteration type to coordinating with architects and expeditors to scheduling inspections and obtaining final sign-offs. Our team has extensive experience with DOB filings across all five boroughs and understands how to keep projects moving efficiently through the regulatory process.
Contact us to learn more about how we can manage the permitting process for your NYC renovation project.