Should You Combine Apartments or Move?

Combining two NYC apartments costs $150,000 to $400,000+ and takes 18 to 30 months. Alteration-CO filing, board timelines, engineering fees, and lender rules.

By J. Sylvester, Designs by D and J — Licensed NYC & NJ General Contractor (NY #623750), MWBE Certified

Combining two apartments makes sense when you want to stay in the building and the combination is physically and legally possible; moving makes sense when the timeline matters more than the location. A combination in Brooklyn or Manhattan typically costs $150,000 to $400,000 or more and realistically takes 18 to 30 months from decision to certificate. Moving costs less time and more money in transaction fees.

Cost figures reflect New York City projects priced in 2026.

How much does it cost to combine two apartments in New York City?

Combining two apartments in New York City typically costs $150,000 to $400,000 or more. The range is wide because the controlling variable is not square footage, it is how much of the work is structural and mechanical rather than cosmetic.

The low end of that range is a combination where the two units share a non-structural demising wall, the kitchens and bathrooms stay where they are, and only a doorway is created. The high end is a combination that removes a load-bearing wall, consolidates two kitchens into one, relocates plumbing, and rebuilds the electrical service for the merged unit. Professional fees, filing costs, and board-required insurance sit on top of construction in both cases.

What is the difference between Alt-1 and Alt-2 when combining apartments?

Alt-1 and Alt-2 were the old BIS filing categories, and they have been retired. In DOB NOW, the Department of Buildings uses two job types: Alteration-CO for work that changes the Certificate of Occupancy, and Alteration for work that does not. Work that used to file as Alt-1 now files as an Alteration-CO. Work that used to file as Alt-2 or Alt-3 now files as an Alteration.

This distinction is the single most important thing to understand about an apartment combination, because combining two apartments into one changes the number of dwelling units in the building, which changes the Certificate of Occupancy. That makes a true combination an Alteration-CO filing, the successor to the old Alt-1. An Alteration-CO requires a registered design professional, a full plan examination, and a new or amended Certificate of Occupancy issued at the end of the job before the space is legally one apartment.

The practical consequence: an Alteration-CO cannot be signed off the way a kitchen renovation can. The job stays open until the amended Certificate of Occupancy is issued, and that final step is the longest unpredictable item in the schedule. Ask your contractor and expediter for their own recent experience on amended Certificate of Occupancy timing in your borough rather than relying on a published average.

Do I need a structural engineer to combine two apartments?

You need a structural engineer whenever the wall between the two apartments carries load, and in most pre-war New York City buildings it does. Structural engineering fees for an apartment combination generally run $3,000 to $8,000.

The engineer determines whether the demising wall is load-bearing, sizes the beam and columns that will replace it, and specifies how the load transfers down through the floors below. In a masonry building that analysis may extend several floors down to the foundation, which is why an engineer sometimes concludes that a combination is not economically feasible. That is a finding worth paying for before you buy the second unit.

How long does a co-op or condo board take to approve an apartment combination?

Board review for a combination commonly runs six to eight weeks and typically takes two rounds of comments. Combinations get more scrutiny than ordinary alterations because they change the building’s share allocation, its Certificate of Occupancy, and its tax lot structure.

Most boards require architect-stamped drawings, a structural engineer’s letter, an executed alteration agreement, contractor insurance naming the corporation and managing agent, and a refundable deposit. Co-op boards must also address share reallocation and maintenance recalculation for the merged unit, which usually requires the corporation’s attorney and sometimes a shareholder vote. Department of Buildings and Landmarks review then add roughly another six to eight weeks after the board signs off.

How long does it take to combine two apartments from start to finish?

A realistic end-to-end timeline is 18 to 30 months from the decision to combine until the amended Certificate of Occupancy is issued. Published estimates are often shorter because they measure only from board approval to construction completion, and they leave out acquisition, design, and the final Certificate of Occupancy.

  • Acquisition and feasibility: securing the second unit and confirming with an engineer that the combination is possible.
  • Design and engineering: architectural drawings, structural analysis, and mechanical coordination.
  • Board review: six to eight weeks, usually two rounds.
  • Department of Buildings and Landmarks review: roughly six to eight weeks after board approval.
  • Construction: commonly five to six months for a straightforward combination, longer where structural work is involved.
  • Sign-off and amended Certificate of Occupancy: the least predictable stage.

Buildings that restrict construction to weekday business hours, or that prohibit work in summer months, extend the construction phase well beyond the nominal duration.

What do lenders require to finance an apartment combination?

Lenders generally will not treat two apartments as one property until the combination is legally complete, which shapes how the project has to be financed. Until the amended Certificate of Occupancy is issued and, in a co-op, the shares are reallocated, the units remain two separate collateral items.

In practice that means buyers usually finance the second unit as its own purchase, carry two loans or two maintenance obligations during construction, and refinance into a single loan after the combination is recorded. Lenders reviewing a combination typically want to see approved architectural plans, the executed alteration agreement, evidence of board approval, and a contractor agreement with a defined scope and price. Co-op lenders will also want the corporation’s written confirmation that shares will be reallocated on completion. Confirm requirements with your specific lender early, because they vary and they drive the acquisition sequence.

When is moving the better decision?

Moving is the better decision when the timeline governs. A combination that takes 18 to 30 months is a poor fit for a family that needs more space before a child starts school, and it is a poor fit for anyone who may relocate within five years.

Moving is also better when the engineer finds the demising wall carries load in a way that cannot be economically transferred, when the board has a history of rejecting combinations, or when the two units are on different floors with no practical stair location. Against that, moving carries its own cost: New York City Real Property Transfer Tax is 1 percent on residential transfers of $500,000 or less and 1.425 percent above $500,000, and it applies to co-op share transfers as well as deeded property. Add state transfer tax, broker commission, attorney fees, any building flip tax, and the buy-side costs on the new home. Confirm the flip tax and any mansion tax exposure with a real estate attorney, because both vary.

Frequently asked questions

Is combining apartments an Alt-1 or an Alt-2?

Neither term is current. Combining two apartments changes the Certificate of Occupancy, so in DOB NOW it files as an Alteration-CO, which replaced the old Alt-1. The old Alt-2 category is now simply an Alteration and applies to work that does not change the Certificate of Occupancy.

Can you combine apartments on different floors?

Yes, if the units are vertically stacked or overlap enough to place an internal stair, and if the floor structure can be opened without compromising load paths. A vertical combination requires a structural engineer and is generally more expensive than a horizontal one because it involves cutting a floor slab or joist system.

Does combining apartments increase property value?

Usually, but not always by the amount spent. A combined three-bedroom generally sells for more than two separate one-bedrooms in the same building, but the premium depends on the building and the layout. A combination that produces an awkward plan with a long corridor or an interior bedroom may not recover its cost.

Do I need Landmarks approval to combine apartments?

If the building is in a landmark district, yes. The Landmarks Preservation Commission requires a permit for any interior work that also requires a Department of Buildings permit. Roughly 95 percent of approvals are issued at staff level, and a Certificate of No Effect is often issued within about 10 business days of a complete application, with a 30 business day statutory decision deadline.

Related reading: If you are weighing scope before committing, see when a full gut renovation isn’t worth it and why Brooklyn brownstone kitchen renovations go over budget.

For full pricing detail, see our guide to what a gut renovation costs in NYC.

Specialty Services

Call Us
BuildZoom.comGeneral Contractors in Brooklyn

Follow our Brooklyn renovation work — add Designs by D & J as a preferred source on Google.